City of Palmdale IT Department

17 public works projects registered with the California Department of Industrial Relations, 2019–2023 · Palmdale.

Projects by year

YearProjectsReported contract value
20238—
20225—
20211—
20201—
20192—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 10
  • Buildings & facilities · 5
  • Electrical, low voltage & AV · 2

Inferred by Atriam from each project's name and description, not reported by the agency.

Latest projects

DateProjectPrime contractorContract amount
Sep 15, 2023Admin Conference Room updateOther——
Aug 30, 2023Aero BulidingOther——
Aug 1, 2023Aero BulidingOther——
Apr 27, 2023DryTown LockersOther——
Apr 20, 2023Oasis DryTownOther——
Apr 10, 2023City Manager Cloud CCTVElectrical, low voltage & AV——
Mar 8, 2023Aero BulidingOther——
Feb 18, 2023MKP Fiber ReplacementOther——
Dec 5, 2022Maintenance Yard / Library FiberBuildings & facilities——
Sep 5, 2022Cultural Center to Data Center Yard FibeBuildings & facilities——
Aug 15, 2022Legacy to Data Center Yard FiberBuildings & facilities——
Aug 15, 2022Playhouse to Data Center Yard FiberBuildings & facilities——
May 20, 2022HR to Data Center Yard FiberBuildings & facilities——
May 5, 2021TOCOther——
Dec 30, 2020Maintenance Yard FiberOther——
Nov 30, 2019CanceledOther——
Oct 25, 2019Network InfrastructureElectrical, low voltage & AV——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.