Pebble Beach Community Services District

26 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Pebble Beach, Monterey County. Reported contract value: $13,834,803.

Projects by year

YearProjectsReported contract value
20262$8,026,516
20254$5,713,287
20242$95,000
20234—
20221—
20211—
20203—
20194—
20181—
20173—
20151—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Sewer & wastewater · 11
  • Other · 5
  • Water · 4
  • Painting & flooring · 3
  • Buildings & facilities · 1
  • Paving & streets · 1
  • HVAC & mechanical · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
REDWOOD PAINTING CO., INC.2$67,750
OUTSOURCE1$7,988,766
LAUREL AG & WATER LLC1$2,777,712
SELDEN & SON1$895,600
ALL STAR PAINTING & MAINTENANCE INC1$95,000

Latest projects

DateProjectPrime contractorContract amount
Jun 12, 2026Undergrounding of Overhead Util, Ph IVOtherOUTSOURCE$7,988,766
Apr 3, 2026Forest Lake Reservoir Piping CoatingWaterREDWOOD PAINTING CO., INC.$37,750
Dec 18, 20252025-26 Seal Rock PS Rehab ProjectSewer & wastewaterLAUREL AG & WATER LLC$2,777,712
Sep 26, 2025Facilities Improvement ProjectHVAC & mechanicalSELDEN & SON$895,600
Jul 24, 2025Seal Rock Pump Station Crane Rehab.WaterREDWOOD PAINTING CO., INC.$30,000
Jan 8, 20252024-2025 Sewer Line Replacement ProjectSewer & wastewater—$2,009,975
Sep 27, 2024PBCSD Buildings Exterior PaintingPainting & flooringALL STAR PAINTING & MAINTENANCE INC$95,000
Jun 17, 2024Recycled Water Pipeline Cathodic ProtectWater——
Aug 7, 2023Carmel Hill Fire Station Improvement ProPaving & streets——
Apr 17, 2023PBCSD Facilities PaintingPainting & flooring——
Apr 17, 2023PBCSD Facilities Painting 2023Painting & flooring——
Jan 2, 20232022 Sewer Replacement ProjectSewer & wastewater——
Dec 26, 2022Pump Station P1 & P2 Rehabilitation ProjSewer & wastewater——
Apr 1, 2021Undergrounding Overhead Utilities, PhaseOther——
Jul 12, 2020Hwy 68 Sewer MHSewer & wastewater——
Jul 12, 2020Hwy 68 PBCSD MHSewer & wastewater——
Apr 20, 2020Wastewater Collection System AssessmentSewer & wastewater——
Nov 5, 2019Emergency Fire Station Driveway RepairOther——
Nov 3, 2019Reclamation Storage Tank RehabilitationBuildings & facilities——
Oct 15, 2019Viscaino Rd. Easement Emergency Sewer ReSewer & wastewater——
May 1, 20192019 Sewer Improvement ProjectSewer & wastewater——
Dec 31, 2018Reclamation Storage Facilities ImprovemeWater——
Oct 23, 2017Seal Rock Pump Station P3 RehabilitationSewer & wastewater——
Aug 21, 2017Lodge Area Sewer Improvement ProjectSewer & wastewater——
Jul 15, 2017UOU PhaseII Private Service Conversion POther——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.