38 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Yuba City, Sutter County. Reported contract value: $22,066,474.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2027 | 1 | $116,019 |
| 2026 | 2 | $100,485 |
| 2025 | 5 | $3,105,653 |
| 2024 | 2 | $132,789 |
| 2023 | 2 | $18,611,528 |
| 2017 | 4 | — |
| 2016 | 13 | — |
| 2015 | 9 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 9
- HVAC & mechanical · 8
- Other · 7
- Painting & flooring · 4
- Electrical, low voltage & AV · 4
- Solar, EV & energy · 3
- Paving & streets · 1
- Design, inspection & consulting · 1
- Roofing · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| ALCO BUILDING SOLUTIONS | 3 | $2,839,992 |
| GAYNOR TELESYSTEMS INC | 3 | $106,471 |
| UNIVERSAL COATINGS INC | 1 | $276,906 |
| JOHN BURGER HEATING & AIR CONDITIONING INC | 1 | $119,000 |
| 4J Construction Services Inc. | 1 | $58,421 |
| CONTI LLC | 1 | $54,156 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| May 28, 2027 | 124 - Boyd Hall floor rehabPaving & streets | ALCO BUILDING SOLUTIONS | $116,019 |
| Aug 27, 2026 | 126-FRA Door Hardware RetrofitElectrical, low voltage & AV | GAYNOR TELESYSTEMS INC | $42,064 |
| Jun 17, 2026 | Harter Dental Lab UpgradeBuildings & facilities | 4J Construction Services Inc. | $58,421 |
| Nov 7, 2025 | 120 Klamath & FRA EMS RehabOther | JOHN BURGER HEATING & AIR CONDITIONING INC | $119,000 |
| Oct 22, 2025 | Project 121 FRA Roof RehabRoofing | UNIVERSAL COATINGS INC | $276,906 |
| Jul 14, 2025 | Project 116 Solar & BESSSolar, EV & energy | ALCO BUILDING SOLUTIONS | $2,645,340 |
| May 15, 2025 | FRA Analog to IPOther | GAYNOR TELESYSTEMS INC | $32,203 |
| Apr 30, 2025 | Project 119 Access ControlsElectrical, low voltage & AV | GAYNOR TELESYSTEMS INC | $32,203 |
| Oct 14, 2024 | Project 114 SC Energy CommissioningDesign, inspection & consulting | ALCO BUILDING SOLUTIONS | $78,633 |
| Jul 16, 2024 | Project 113 Board Room A/V UpgradeElectrical, low voltage & AV | CONTI LLC | $54,156 |
| Dec 17, 2023 | Shady Creek HVAC RetrofitHVAC & mechanical | — | — |
| Feb 10, 2023 | Project 95Buildings & facilities | — | $18,611,528 |
| Oct 1, 2017 | SmartWatt Task Order 5Other | — | — |
| Jul 1, 2017 | 68-1718-IT HVACHVAC & mechanical | — | — |
| May 1, 2017 | Shady Creek Walk-in RefrigeratorHVAC & mechanical | — | — |
| Mar 14, 2017 | FRA DF Carpet ReplacementPainting & flooring | — | — |
| Dec 31, 2016 | 68 - HVAC ReplacementHVAC & mechanical | — | — |
| Dec 31, 2016 | 68 - HVAC 3HVAC & mechanical | — | — |
| Dec 31, 2016 | 68 - HVAC 2HVAC & mechanical | — | — |
| Dec 31, 2016 | 68 - Annex CarpetPainting & flooring | — | — |
| Dec 18, 2016 | 1617 - Glass ReplacementBuildings & facilities | — | — |
| Dec 18, 2016 | 68 - Storefront Door InfillBuildings & facilities | — | — |
| Nov 13, 2016 | Project 68 - ACOther | — | — |
| Nov 1, 2016 | SmartWatt Task Order 4Solar, EV & energy | — | — |
| Nov 1, 2016 | SmartWatt Task Order 3Solar, EV & energy | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.