107 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Placerville, El Dorado County. Reported contract value: $32,333,463.

Projects by year

YearProjectsReported contract value
20267$1,574,695
202511$25,079,731
202410$440,946
202317$974,088
20226—
20218—
20207—
201912$293,583
201813—
20172$3,970,420
20164—
20152—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Paving & streets · 38
  • Storm drain & flood control · 18
  • Other · 16
  • Sewer & wastewater · 12
  • Bridges & structures · 5
  • Electrical, low voltage & AV · 4
  • Water · 3
  • Parks, landscape & fields · 3
  • Buildings & facilities · 3
  • HVAC & mechanical · 2
  • Design, inspection & consulting · 1
  • Traffic & signals · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
C E COX ENGINEERING INC4$1,180,708
SKI AIR INCORPORATED2$18,000
Fibertel LLC1$20,198,943
Bess US Inc.1$974,088
DOUG VEERKAMP GENERAL ENGINEERING INC1$799,534
ENGEO INCORPORATED1$293,583
ERS INDUSTRIAL SERVICES INC1$178,000
M P ENVIRONMENTAL SERVICES INC1$175,000
F.D. THOMAS, INC.1$146,261
PROUD CONSTRUCTION1$64,487
MIRACLE CONSTRUCTION COMPANY INCORPORATED DBA MIRACLE PLAYSYSTEMS1$16,618
GEOCON CONSULTANTS, INC1$11,500
R.E.Y. ENGINEERS, INC.1$9,000

Latest projects

DateProjectPrime contractorContract amount
Jun 25, 2026Upper Broadway & Point View Storm DrainStorm drain & flood controlC E COX ENGINEERING INC$287,584
Jun 18, 2026Giovanni Road Sewer Line ReplacementSewer & wastewaterC E COX ENGINEERING INC$148,316
May 15, 2026Primary Clarifier #1 CoatingOtherF.D. THOMAS, INC.$146,261
May 15, 2026Digester #1 CleaningOtherM P ENVIRONMENTAL SERVICES INC$175,000
Apr 28, 2026Thompson Way Repaving Project Phase 2Storm drain & flood controlDOUG VEERKAMP GENERAL ENGINEERING INC$799,534
Mar 24, 2026Digester Room ACBuildings & facilitiesSKI AIR INCORPORATED$9,000
Mar 24, 2026Digester Room ACOtherSKI AIR INCORPORATED$9,000
Nov 12, 2025Bedford Ave Curb Ramp & Main St SidewalkPaving & streetsC E COX ENGINEERING INC$31,818
Sep 23, 2025Pickleball Court Slope RepairOther—$59,516
Sep 9, 2025Placerville Dr Ped ConnectivityPaving & streets—$1,570,799
Sep 2, 2025Placerville Fiber NetworkElectrical, low voltage & AVFibertel LLC$20,198,943
Jul 24, 2025Secondary Clarifier Launder CoatingOtherERS INDUSTRIAL SERVICES INC$178,000
Jul 8, 2025Smith Flat Road Storm Drain and PavingSewer & wastewater—$2,064,482
Jul 8, 2025Secondary Clarifier Launders RecoatingOther—$178,300
Jul 8, 2025Lion's Park - Slide RepairPaving & streets—$3,778
Jun 24, 2025City Park - Playground RepairsParks, landscape & fieldsMIRACLE CONSTRUCTION COMPANY INCORPORATED DBA MIRACLE PLAYSYSTEMS$16,618
May 13, 2025Thompson/Sherman Paving Project Phase 1Sewer & wastewaterC E COX ENGINEERING INC$712,990
Feb 11, 2025Downtown Public Restroom Remodel (42418Electrical, low voltage & AVPROUD CONSTRUCTION$64,487
Dec 19, 2024Mallard Lane MaintenanceOtherGEOCON CONSULTANTS, INC$11,500
Dec 10, 2024Storm Drain Replacement - Upper BroadwayDesign, inspection & consultingR.E.Y. ENGINEERS, INC.$9,000
Jun 25, 2024Secondary Clarifier #1 CoatingOther—$167,750
May 28, 2024Thompson Way Paving ProjectPaving & streets—$227,700
May 27, 2024Secondary Clarifier No. 3 Drive UnitOther——
May 14, 2024El Dorado Trail RepairParks, landscape & fields—$24,996
Mar 18, 2024Bee Storm Storm Drain RepairStorm drain & flood control——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.