50 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Antioch, Contra Costa County. Reported contract value: $190,960,599.

Projects by year

YearProjectsReported contract value
20262$164,760,000
20251$1,260,000
20246$18,113,249
20235$95,000
20226—
20213—
20201—
20196—
20183—
20176—
20162—
20156—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 16
  • Sewer & wastewater · 14
  • Electrical, low voltage & AV · 7
  • Water · 6
  • Buildings & facilities · 3
  • Paving & streets · 2
  • Roofing · 1
  • Painting & flooring · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
FLATIRON DRAGADOS CONSTRUCTORS INC1$164,715,000
SHIMMICK CONSTRUCTION COMPANY INC1$14,540,000
MOUNTAIN CASCADE INC1$6,732,350
Rural/Metro Fire Dept.,Inc1$95,000
ACE ELECTRIC MOTOR & PUMP CO1$45,000
TABER DRILLING1$25,000

Latest projects

DateProjectPrime contractorContract amount
Sep 9, 2026Secondary Process Improvements Phase 1Sewer & wastewaterFLATIRON DRAGADOS CONSTRUCTORS INC$164,715,000
Jun 1, 2026Fan BalancingWaterACE ELECTRIC MOTOR & PUMP CO$45,000
Jun 16, 2025MH Phase 2 - Arcy Lane RehabSewer & wastewater—$1,260,000
Sep 11, 2024IT OFFICE REMODEL/SITE SECURITY IMP.Painting & flooring—$163,100
Sep 9, 2024HHW Management ServicesOther—$2,948,400
Aug 14, 2024Cogen System ImprovementsOtherSHIMMICK CONSTRUCTION COMPANY INC$14,540,000
Jul 17, 2024Secondary Process Improvements - GeotechOtherTABER DRILLING$25,000
Jul 1, 2024Tower Trickling Filters RehabilitationOther—$436,749
Apr 5, 2024POC FURNITURE INSTALLATIONOther——
Oct 2, 2023Bay Point Collection System Point RepairSewer & wastewater——
Sep 1, 2023Digester No. 2 RehabilitationPaving & streets——
Jul 20, 2023Confined Space ServicesOtherRural/Metro Fire Dept.,Inc$95,000
Jun 19, 2023Manhole, Gravity Interceptor, and EasemeSewer & wastewater——
Jun 16, 2023RWF Sand Pump Piping Replacement ProjectOther——
Dec 5, 2022Camp Stoneman Force Main RepairOther——
Oct 19, 2022Manhole, Gravity Interceptor, and EasemeSewer & wastewater——
Jul 11, 2022Willow Pass Interceptor RepairOther——
Jun 20, 2022Hill Street Emergency RepairSewer & wastewater——
Jun 16, 2022POC Conduit and Generator Wiring RepairElectrical, low voltage & AV——
Jun 10, 2022Onsite Fueling Station and Generator FueElectrical, low voltage & AV——
Nov 7, 2021RWF Sand Filter Intermittent Backwash ImOther——
Sep 27, 2021Bridgehead Pipeline Replacement ProjectSewer & wastewater——
Feb 14, 2021Treatment Plant Switchgear ReplacementElectrical, low voltage & AV——
Sep 14, 2020Bridgehead Pipeline Replacement ProjectSewer & wastewater——
Nov 28, 2019Headworks ImprovementsBuildings & facilities——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.