City of South Lake Tahoe, Lake Tahoe Airport

30 public works projects registered with the California Department of Industrial Relations, 2000–2024 · South Lake Tahoe.

Projects by year

YearProjectsReported contract value
20241—
202312—
20213—
20202—
20195—
20184—
20172—
20001—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 9
  • Paving & streets · 7
  • Buildings & facilities · 5
  • Electrical, low voltage & AV · 3
  • Roofing · 2
  • HVAC & mechanical · 2
  • Painting & flooring · 1
  • Storm drain & flood control · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Latest projects

DateProjectPrime contractorContract amount
Jun 20, 2024Airport Deck SealingOther——
Dec 5, 2023AIRPORT SECOND FLOOR BATHROOMBuildings & facilities——
Dec 3, 2023CANCELLED-Airport OfficeBuildings & facilities——
Dec 2, 2023Airport LocksetsOther——
Nov 5, 2023AIRPORT BATHROOM TILE AND PARTICION REPLPainting & flooring——
Nov 1, 2023City Wide Snow RemovalOther——
Sep 14, 2023Airfield Striping PaintPaving & streets——
Sep 14, 2023HVAC AIRPORT BATHROOM REPAIRHVAC & mechanical——
Sep 12, 2023Airport Hazardous Fuels ReductionHVAC & mechanical——
Aug 15, 2023Hangar Taxilane Rehab ProjectOther——
Jun 27, 2023Fire Station #4 Roof RepairRoofing——
Jun 27, 2023Airport Crack SealPaving & streets——
Mar 24, 2023Hangar Door ReconstructionBuildings & facilities——
Nov 1, 202121/22 AIRPORT SNOW REMOVALOther——
Oct 6, 2021Somermeir Hangar Code RepairsElectrical, low voltage & AV——
May 3, 2021General Aviation Ramp Reconstruction-PhaPaving & streets——
Nov 1, 202020/21 Airport Contract Snow RemovalOther——
May 26, 20202020 South Hangar Door MaintenanceBuildings & facilities——
Nov 1, 2019Airport Snow Removal 2019/2020Paving & streets——
Sep 3, 2019General Aviation Ramp Reconstruction-PhaOther——
Sep 3, 2019Install Replacement Diesel GeneratorElectrical, low voltage & AV——
May 10, 2019Rehabilitate Terminal ApronPaving & streets——
May 1, 2019Airport Solar Power Power Purchase AgreeRoofing——
Sep 3, 201846 Acre Airport Vegetative ManagmentOther——
Sep 3, 2018Security Upgrades City Admin Bldg./AirpoElectrical, low voltage & AV——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.