City of Palo Alto Utilities

17 public works projects registered with the California Department of Industrial Relations, 2019–2026 · Palo Alto, Santa Clara County. Reported contract value: $25,379,215.

Projects by year

YearProjectsReported contract value
20262$763,000
20253$23,707,409
20242$908,806
20233—
20222—
20212—
20202—
20191—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 7
  • Water · 3
  • Buildings & facilities · 2
  • Electrical, low voltage & AV · 2
  • Bridges & structures · 1
  • Design, inspection & consulting · 1
  • Concrete & masonry · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
M P NEXLEVEL OF CALIFORNIA INC1$14,660,205
WRA INC.1$908,806
BLACKHAWK PAINTING COMPANY INC1$735,500
GRISWOLD INDUSTRIES1$85,000
BAILEY FENCE COMPANY, INC.1$27,500
VIP POWERLINE CORP1—

Latest projects

DateProjectPrime contractorContract amount
Aug 10, 2026Substation Painting ContractElectrical, low voltage & AVBLACKHAWK PAINTING COMPANY INC$735,500
Jun 16, 2026East Meadow Substation Fence RepairBuildings & facilitiesBAILEY FENCE COMPANY, INC.$27,500
Oct 22, 2025Gas Main Replacement 25 (GMR25)Other—$8,962,204
Oct 6, 2025Utility Trench & Substructure (2026-2029OtherM P NEXLEVEL OF CALIFORNIA INC$14,660,205
Mar 3, 2025Water Trans Valve RebuildOtherGRISWOLD INDUSTRIES$85,000
Jun 4, 2024Arastradero Creek Permanent RestorationOtherWRA INC.$908,806
Jan 15, 2024Gas Main Replacement 24BOther——
Sep 19, 2023Electric Utility Construction Project/SeElectrical, low voltage & AVVIP POWERLINE CORP—
Feb 1, 2023Park Reservoir Engineering AssessmentWater——
Jan 18, 2023Two Turnouts ProjectOther——
Dec 20, 2022Gas Main Replacement 24A ProjectBuildings & facilities——
Oct 3, 2022Multifamily Residential ProgramOther——
Nov 7, 2021Advanced Metering Infrastructure ProjectDesign, inspection & consulting——
Nov 1, 2021Recoating Natural Gas Steel Main CrossinBridges & structures——
Aug 3, 2020Mayfield Reservoir Vent Screens and CracWater——
Feb 16, 2020On-Call Testing ServicesConcrete & masonry——
Oct 15, 2019Water Main Replacement Project 27AWater——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.