22 public works projects registered with the California Department of Industrial Relations, 2020–2024 · Rio Vista.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2024 | 3 | — |
| 2023 | 2 | — |
| 2022 | 7 | — |
| 2021 | 2 | — |
| 2020 | 8 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 5
- Parks, landscape & fields · 5
- Water · 4
- Paving & streets · 3
- Sewer & wastewater · 3
- Electrical, low voltage & AV · 1
- Bridges & structures · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| May 1, 2024 | ARPA River Road WaterWater | — | — |
| Feb 11, 2024 | Airport Road Striping ImprovementsPaving & streets | — | — |
| Feb 5, 2024 | HSIP Cycle 10 Pedestrian CrossingsOther | — | — |
| Mar 20, 2023 | Egbert Field Grandstand ProjectParks, landscape & fields | — | — |
| Jan 31, 2023 | Repair of Grandstand Cover at Egbert FieOther | — | — |
| Oct 31, 2022 | 2022 Emergency Waterline ReplacementWater | — | — |
| Oct 3, 2022 | St Francis Way Water Transmission LineWater | — | — |
| Jun 30, 2022 | HSIP Cycle 9 Grant Funded Pedestrian CroOther | — | — |
| Jan 31, 2022 | 2021 Northwest Sewer CCTV Inspection ProSewer & wastewater | — | — |
| Jan 31, 2022 | 2020 & 2021 Water and Sewer CIPSewer & wastewater | — | — |
| Jan 2, 2022 | Promenade Park Tension Shade Sail StructParks, landscape & fields | — | — |
| Jan 2, 2022 | Rio Vista Municipal Airport Electrical IElectrical, low voltage & AV | — | — |
| Jun 1, 2021 | LGI Neighborhood Park Improvements FallParks, landscape & fields | — | — |
| May 17, 2021 | LGI Neighborhood Park PlaygroundsParks, landscape & fields | — | — |
| Dec 6, 2020 | LGI Neighborhood ParkParks, landscape & fields | — | — |
| Jul 20, 2020 | Northwest Wastewater Treatment Plant MemSewer & wastewater | — | — |
| Jun 19, 2020 | Energy Efficiency Upgrades Phase 2Other | — | — |
| May 18, 2020 | City of Rio Vista Boat Launch Ramp ReplaBridges & structures | — | — |
| May 18, 2020 | Montezuma Hills Road Pedestrian PathPaving & streets | — | — |
| Apr 26, 2020 | Corp Yard Emergency Power Backup ImproveOther | — | — |
| Apr 1, 2020 | Public Works Corporation Yard ImprovemenPaving & streets | — | — |
| Jan 26, 2020 | 2019 Water Meter Project Ph 2Water | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.