North Tahoe Public Utility District
83 public works projects registered with the California Department of Industrial Relations, 2013–2026 · Tahoe Vista, Placer County. Reported contract value: $12,250,693.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 10 | $4,985,866 |
| 2025 | 13 | $6,629,698 |
| 2024 | 8 | $635,129 |
| 2023 | 9 | — |
| 2022 | 6 | — |
| 2021 | 6 | — |
| 2020 | 8 | — |
| 2019 | 6 | — |
| 2018 | 1 | — |
| 2017 | 5 | — |
| 2016 | 5 | — |
| 2015 | 4 | — |
| 2014 | 1 | — |
| 2013 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Water · 18
- Sewer & wastewater · 17
- Paving & streets · 12
- Buildings & facilities · 7
- Parks, landscape & fields · 6
- Electrical, low voltage & AV · 5
- Design, inspection & consulting · 4
- Other · 4
- Painting & flooring · 3
- Plumbing & restrooms · 2
- Roofing · 2
- Demolition & site work · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| K G WALTERS CONSTRUCTION CO INC | 3 | $3,097,000 |
| F W CARSON CO | 2 | $1,702,006 |
| LUMOS & ASSOCIATES, INC. | 2 | $575,080 |
| VINCIGUERRA CONSTRUCTION INC | 1 | $1,425,280 |
| SFT CONSTRUCTION CORP | 1 | $1,104,480 |
| PHOENIX WATER SOLUTIONS | 1 | $612,935 |
| GREEN BEAR CONSTRUCTION INC | 1 | $411,600 |
| RUPPERT INC | 1 | $350,625 |
| GSP CONSTRUCTION INC | 1 | $346,000 |
| DIABLO ROOFING INC | 1 | $156,600 |
| WEST COAST PAVING, INC. | 1 | $100,000 |
| PR Design and Engineering Inc. | 1 | $56,000 |
| JACOB LAUTER | 1 | $51,000 |
| Carson Pump LLC | 1 | $32,300 |
| YESCO LLC DBA YESCO SIGNS LLC | 1 | $25,866 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Oct 13, 2026 | C1 & D3 Sewage Pump Station ImprovementSewer & wastewater | K G WALTERS CONSTRUCTION CO INC | $1,051,000 |
| Oct 13, 2026 | 2026 Sewer Export Forcemain Emergency ReSewer & wastewater | K G WALTERS CONSTRUCTION CO INC | $449,000 |
| Sep 11, 2026 | North Tahoe Event Center Tree LightingElectrical, low voltage & AV | JACOB LAUTER | $51,000 |
| Aug 4, 2026 | Summer 2026 Pavement MaintenancePaving & streets | LAKESIDE PAVING AND SEALING INC | $21,000 |
| May 12, 2026 | 2026 Replacement of Asphalt Concrete...Paving & streets | F W CARSON CO | $50,000 |
| Apr 23, 2026 | Carnelian Well RehabilitationWater | Carson Pump LLC | $32,300 |
| Apr 15, 2026 | Snow Creek Connector TrailDesign, inspection & consulting | LUMOS & ASSOCIATES, INC. | $259,598 |
| Apr 15, 2026 | PEM Pinedrop Trail Reconstruction DesignDesign, inspection & consulting | LUMOS & ASSOCIATES, INC. | $315,482 |
| Apr 14, 2026 | 2026 Water Main ReplacementWater | F W CARSON CO | $1,652,006 |
| Apr 14, 2026 | Annex Building Garage and Seismic ImprovDemolition & site work | SFT CONSTRUCTION CORP | $1,104,480 |
| Oct 14, 2025 | NTEC South Restroom RenovationPlumbing & restrooms | GSP CONSTRUCTION INC | $346,000 |
| Oct 14, 2025 | C2, D4, and D6 Sewage Pump Station ImproSewer & wastewater | K G WALTERS CONSTRUCTION CO INC | $1,597,000 |
| Sep 9, 2025 | Corporation Yard Master Plan Phase 2Design, inspection & consulting | PR Design and Engineering Inc. | $56,000 |
| Aug 12, 2025 | Speckled Water Service Line & PRV InstalWater | GREEN BEAR CONSTRUCTION INC | $411,600 |
| Jul 8, 2025 | NTPUD Smart Water Meter InstallationWater | PHOENIX WATER SOLUTIONS | $612,935 |
| May 13, 2025 | NTRP Trail ExtensionParks, landscape & fields | — | $1,451,471 |
| May 2, 2025 | Community Gathering Space ImprovementPaving & streets | RUPPERT INC | $350,625 |
| Apr 29, 2025 | NTEC Sign InstallationBuildings & facilities | YESCO LLC DBA YESCO SIGNS LLC | $25,866 |
| Apr 8, 2025 | 2025 Replacement of Asphalt Concrete InPaving & streets | WEST COAST PAVING, INC. | $100,000 |
| Mar 20, 2025 | Spring 2025 Lower Lateral LiningSewer & wastewater | — | $48,000 |
| Mar 11, 2025 | Trout Avenue Waterline ReplacementWater | VINCIGUERRA CONSTRUCTION INC | $1,425,280 |
| Feb 11, 2025 | NTPUD HQ Building Roof ReplacementRoofing | DIABLO ROOFING INC | $156,600 |
| Feb 6, 2025 | NTEC - 2025 Lakeview Room ImprovementsBuildings & facilities | — | $48,321 |
| Sep 9, 2024 | Brockway Fire Protection Water InfrastruWater | — | — |
| Jul 29, 2024 | Carnelian Bay Landscape RemediationSewer & wastewater | — | $35,217 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.
Do you bid public works?
Find your license and claim your free Atriam profile. It lists the public works projects registered under your license.