OLIVENHAIN MUNICIPAL WATER DISTRICT
365 public works projects registered with the California Department of Industrial Relations, 2011–2026 · Encinitas, San Diego County. Reported contract value: $13,303,299.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 7 | $271,560 |
| 2025 | 12 | $9,673,923 |
| 2024 | 16 | $3,357,816 |
| 2023 | 11 | — |
| 2022 | 14 | — |
| 2021 | 6 | — |
| 2020 | 19 | — |
| 2019 | 23 | — |
| 2018 | 15 | — |
| 2017 | 65 | — |
| 2016 | 110 | — |
| 2015 | 64 | — |
| 2011 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 115
- Water · 59
- Traffic & signals · 50
- Paving & streets · 38
- Parks, landscape & fields · 35
- Buildings & facilities · 21
- Sewer & wastewater · 12
- Electrical, low voltage & AV · 9
- Painting & flooring · 5
- Concrete & masonry · 4
- HVAC & mechanical · 4
- Demolition & site work · 3
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| CASS ARRIETA | 7 | $4,723,003 |
| JOE'S PAVING COMPANY INC | 4 | $296,239 |
| ZEBRON CONTRACTING INC | 3 | $267,070 |
| UTILITY SERVICE CO INC | 1 | $499,249 |
| USG West, Inc. | 1 | $499,249 |
| FARWEST CORROSION CONTROL COMPANY | 1 | $443,388 |
| T C CONSTRUCTION COMPANY INC | 1 | $200,000 |
| HDR ENGINEERING, INC. | 1 | $135,940 |
| BRIGHTVIEW LANDSCAPE SERVICES, INC. | 1 | $105,192 |
| ANGUS ASPHALT INC | 1 | $21,900 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Aug 8, 2026 | Calle Barcelona Emergency Leak RepairWater | CASS ARRIETA | $85,000 |
| Jun 5, 2026 | Quinta, Del Rey, Dalia Asphalt RepairsPaving & streets | JOE'S PAVING COMPANY INC | $31,638 |
| May 26, 2026 | Collection System Manhole RehabilitationSewer & wastewater | ZEBRON CONTRACTING INC | $31,480 |
| Apr 15, 2026 | EDGEFIELD LANE WATER MAIN REPAIR PROJECTWater | CASS ARRIETA | $55,000 |
| Mar 10, 2026 | Valve Replacement AC RestorationOther | JOE'S PAVING COMPANY INC | $18,601 |
| Mar 10, 2026 | El Camino Leak Repair ProjectOther | CASS ARRIETA | $16,785 |
| Feb 11, 2026 | DCMWTP Bridge Crane Rep/ImpBridges & structures | — | $33,056 |
| Dec 15, 2025 | Farol Place Emergency Asphalt RepairWater | JOE'S PAVING COMPANY INC | $16,000 |
| Nov 19, 2025 | Landscape Services & Multiple SitesParks, landscape & fields | BRIGHTVIEW LANDSCAPE SERVICES, INC. | $105,192 |
| Sep 29, 2025 | OTP-1 Emergency Pipeline RepairDemolition & site work | CASS ARRIETA | $50,000 |
| Sep 17, 2025 | Azahar/Cadencia/Romeria/Aldea EmergencyWater | CASS ARRIETA | $4,342,218 |
| Aug 20, 2025 | Cadencia Street 6-in Water Main RepairWater | JOE'S PAVING COMPANY INC | $230,000 |
| Jun 18, 2025 | OMWD Cathodic Protection ImprovementsOther | FARWEST CORROSION CONTROL COMPANY | $443,388 |
| Apr 23, 2025 | Dusty Trail Pipeline Design/ReplacementParks, landscape & fields | HDR ENGINEERING, INC. | $135,940 |
| Apr 17, 2025 | Asphalt Repair & Seal Coat at Peay Resv.Paving & streets | ANGUS ASPHALT INC | $21,900 |
| Mar 19, 2025 | 4SWRF Headworks Screening & Strainer ImpBuildings & facilities | — | $4,095,200 |
| Feb 19, 2025 | DCMWTP Bridge Crane RehabilitationBridges & structures | — | $64,995 |
| Feb 10, 2025 | Gaty 1 Reservoir Top Liner RemovalWater | — | $19,090 |
| Feb 6, 2025 | Firehouse SPS Forcemain Emergency LeakSewer & wastewater | CASS ARRIETA | $150,000 |
| Dec 18, 2024 | Olivenhain Road Emergency Leak RepairTraffic & signals | CASS ARRIETA | $24,000 |
| Dec 11, 2024 | Olivenhain Reservoirs Safety ImprovementWater | USG West, Inc. | $499,249 |
| Dec 11, 2024 | OMWD Reservoir Safety ImprovementsWater | UTILITY SERVICE CO INC | $499,249 |
| Oct 16, 2024 | Firehouse SPS Wet-well Liner ReplacementWater | ZEBRON CONTRACTING INC | $77,510 |
| Sep 18, 2024 | 12" Recycled Water Main Emergency LeakWater | T C CONSTRUCTION COMPANY INC | $200,000 |
| Aug 14, 2024 | Gardendale/Village Park PRS ReplacementParks, landscape & fields | — | $1,899,728 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.