375 public works projects registered with the California Department of Industrial Relations, 2000–2026 · Anaheim, Orange County. Reported contract value: $40,458,039.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 67 | $9,991,087 |
| 2025 | 99 | $18,501,333 |
| 2024 | 107 | $10,372,017 |
| 2023 | 49 | $182,128 |
| 2022 | 6 | — |
| 2019 | 6 | — |
| 2018 | 6 | — |
| 2017 | 12 | — |
| 2000 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 72
- Other · 71
- Electrical, low voltage & AV · 33
- HVAC & mechanical · 32
- Roofing · 31
- Water · 27
- Parks, landscape & fields · 16
- Fire & life safety · 13
- Painting & flooring · 13
- Elevators & conveying · 11
- Storm drain & flood control · 9
- Demolition & site work · 8
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| BRONCO HEATING & AIR | 14 | $1,544,531 |
| SIEMENS INDUSTRY INC | 12 | $623,128 |
| PACIFIC MECHANICAL CONSTRUCTION | 10 | $2,753,405 |
| MORROW - MEADOWS CORPORATION | 9 | $1,529,647 |
| ENERGY MANAGEMENT SOLUTIONS | 8 | $861,492 |
| BP IRON INC | 7 | $723,123 |
| JEMSTAR INC DBA JEMSTAR CONSTRUCTION SERVICES | 7 | $227,534 |
| VETERANS COMMUNICATION SERVICES INCORPORATED | 7 | $209,878 |
| TRANE U S INC | 6 | $406,935 |
| BEST CONTRACTING SERVICES INC | 5 | $2,367,409 |
| WILLIAM KELLER | 5 | $536,848 |
| Vicon Enterprise Inc | 4 | $2,839,865 |
| Carmody Construction Company | 4 | $834,640 |
| E & L BUILDING COMPANY INC | 4 | $728,303 |
| ATI RESTORATION, LLC | 4 | $169,678 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Oct 6, 2026 | ENERGY FIELDParks, landscape & fields | Vicon Enterprise Inc | $375,500 |
| Oct 2, 2026 | 4950 Beam RepairsOther | PACIFIC MECHANICAL CONSTRUCTION | $159,000 |
| Sep 30, 2026 | AWT 1ST FLOOR COLLECTIONS CARPET INSTALLPainting & flooring | SIGNATURE FLOORING INC | $36,050 |
| Sep 30, 2026 | STORE ONE GLASS REHABOther | ANAHEIM GLASS INC | $35,527 |
| Sep 30, 2026 | DTCC - CLEAR ROOF DRAINSRoofing | VERNE'S PLUMBING INC | $17,750 |
| Sep 24, 2026 | APU SUB MEDIA RPLCMTOther | WILLIAM KELLER | $62,712 |
| Sep 24, 2026 | WELL 40 PIP DISCHARGEWater | BRONCO HEATING & AIR | $29,886 |
| Sep 16, 2026 | CITY HALL ADA SLIDING DOORSBuildings & facilities | ACTION DOOR REPAIR CORPORATION | $32,189 |
| Sep 14, 2026 | AWT ELEVATOR ACCESS BADGE READER UPGRADEElevators & conveying | MCM INTEGRATED SYSTEMS INC | $19,570 |
| Sep 9, 2026 | ANAHEIM ROOF HATCH IMPROVEMENTSRoofing | PACIFIC MECHANICAL CONSTRUCTION | $167,314 |
| Sep 4, 2026 | AWT Fire Control Panel DevicesOther | WESTERN STATES FIRE PROTECTION COMPANY | $31,440 |
| Sep 2, 2026 | APU Substation Water Treatment Annual SeWater | WILLIAM KELLER | $15,480 |
| Sep 1, 2026 | APU SUBSTATION EVAP & HVAC MAINTENANCEHVAC & mechanical | ALLISON MECHANICAL, INC | $110,517 |
| Aug 27, 2026 | STORE ONEOther | ALLISON MECHANICAL, INC | $75,500 |
| Aug 25, 2026 | RFWOP - Design Build for WPD TIBuildings & facilities | Carmody Construction Company | $649,513 |
| Aug 21, 2026 | ROOF REPAIRS, FS 1 AND DTCCRoofing | JEMSTAR INC DBA JEMSTAR CONSTRUCTION SERVICES | $56,477 |
| Aug 14, 2026 | CH-2ND FLOOR VOIP CABLINGElectrical, low voltage & AV | VETERANS COMMUNICATION SERVICES INCORPORATED | $18,720 |
| Aug 13, 2026 | ANAHEIM SUBSTATION MEDIA RPLCMTOther | WILLIAM KELLER | $99,712 |
| Aug 7, 2026 | APD-GARDENWALK FIBER AND DATA CABLINGElectrical, low voltage & AV | VETERANS COMMUNICATION SERVICES INCORPORATED | $40,041 |
| Aug 4, 2026 | FS 11 - EMERGENCY ROOF REPAIRSRoofing | JEMSTAR INC DBA JEMSTAR CONSTRUCTION SERVICES | $22,700 |
| Aug 3, 2026 | EUC South Campus ConstructionWater | PACIFIC MECHANICAL CONSTRUCTION | $959,480 |
| Jul 24, 2026 | APU-TELCOM GROUP-FIBER OPTICSElectrical, low voltage & AV | VETERANS COMMUNICATION SERVICES INCORPORATED | $58,500 |
| Jul 20, 2026 | Euclid Fence Improvements ProjectBuildings & facilities | PACIFIC MECHANICAL CONSTRUCTION | $339,859 |
| Jul 17, 2026 | AWT-WINDOW CAULKINGBuildings & facilities | PACIFIC MECHANICAL CONSTRUCTION | $93,600 |
| Jul 8, 2026 | CANYON POWER PLANT GEAROther | — | $29,846 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.