Charter Oak Unified School District
173 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Covina, Los Angeles County. Reported contract value: $7,334,452.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 8 | $546,192 |
| 2025 | 2 | $346,378 |
| 2024 | 13 | $6,146,882 |
| 2023 | 12 | — |
| 2022 | 3 | — |
| 2021 | 2 | — |
| 2020 | 3 | — |
| 2019 | 15 | — |
| 2018 | 23 | — |
| 2017 | 27 | — |
| 2016 | 34 | — |
| 2015 | 30 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 55
- Buildings & facilities · 27
- Parks, landscape & fields · 20
- Painting & flooring · 17
- Paving & streets · 12
- Electrical, low voltage & AV · 9
- Roofing · 8
- HVAC & mechanical · 8
- Elevators & conveying · 6
- Solar, EV & energy · 6
- Traffic & signals · 2
- Plumbing & restrooms · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| SOLAR OPTIMUM DESIGN & ELECTRICAL | 4 | $2,447,640 |
| COURTNEY INC | 3 | $757,818 |
| Mike's Custom Flooring, Inc. | 2 | $90,140 |
| GENESIS FLOOR COVERING INC | 2 | $68,224 |
| Southland Roofing Inc. | 1 | $862,000 |
| PLAYPOWER LT FARMINGTON, INC | 1 | $218,105 |
| BAUTISTA ASBESTOS ENVIRONMENTAL | 1 | $96,143 |
| SIERRA SCHOOL EQUIPMENT COMPANY | 1 | $93,392 |
| FLOOR TECH AMERICA INC | 1 | $51,378 |
| WARREN COLLINS AND ASSOCIATES INC DBA COLLINS COMPANY | 1 | $39,886 |
| MARISCAL PAINTING | 1 | $35,000 |
| AXXESS DOOR CORP | 1 | $33,693 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Aug 24, 2026 | COHS WindscreenBuildings & facilities | WARREN COLLINS AND ASSOCIATES INC DBA COLLINS COMPANY | $39,886 |
| Jun 15, 2026 | Glen Oak ES- EpoxyOther | GENESIS FLOOR COVERING INC | $38,967 |
| Jun 15, 2026 | WASHINGTON ES- EPOXYOther | GENESIS FLOOR COVERING INC | $29,258 |
| May 22, 2026 | Asbestos Abatment ProjectDemolition & site work | BAUTISTA ASBESTOS ENVIRONMENTAL | $96,143 |
| May 19, 2026 | GLEN OAK FLOORINGPainting & flooring | Mike's Custom Flooring, Inc. | $64,351 |
| May 19, 2026 | CEDARGROVE DOORSBuildings & facilities | AXXESS DOOR CORP | $33,693 |
| May 14, 2026 | GLEN OAK FLOORINGPainting & flooring | Mike's Custom Flooring, Inc. | $25,790 |
| Jan 9, 2026 | Cedargrove PlaygroundParks, landscape & fields | PLAYPOWER LT FARMINGTON, INC | $218,105 |
| Nov 6, 2025 | WILLOW FLOORINGPainting & flooring | FLOOR TECH AMERICA INC | $51,378 |
| Apr 17, 2025 | COUSD Roofing ProjectRoofing | COURTNEY INC | $295,000 |
| Nov 21, 2024 | COUSD Adult Education Roofing ProjectRoofing | Southland Roofing Inc. | $862,000 |
| Jul 24, 2024 | Theater PaintPainting & flooring | MARISCAL PAINTING | $35,000 |
| Jul 23, 2024 | Solar Panels/Prkng LotsSolar, EV & energy | — | $2,447,640 |
| Jun 30, 2024 | Charter Oak High School Solar ProjectSolar, EV & energy | SOLAR OPTIMUM DESIGN & ELECTRICAL | $965,005 |
| Jun 30, 2024 | Royal Oak Middle School Solar ProjectSolar, EV & energy | SOLAR OPTIMUM DESIGN & ELECTRICAL | $655,051 |
| Jun 30, 2024 | Cedargrove ES Solar ProjectSolar, EV & energy | SOLAR OPTIMUM DESIGN & ELECTRICAL | $410,000 |
| Jun 30, 2024 | District Office Solar ProjectSolar, EV & energy | SOLAR OPTIMUM DESIGN & ELECTRICAL | $417,584 |
| Jun 3, 2024 | Ruddock (Sonrise) RoofingRoofing | COURTNEY INC | $167,818 |
| Jun 1, 2024 | Ruddock RoofingRoofing | — | — |
| Apr 15, 2024 | DSC RoofingRoofing | — | — |
| Apr 4, 2024 | Theater SeatingOther | — | $93,392 |
| Mar 12, 2024 | Theater SeatingOther | SIERRA SCHOOL EQUIPMENT COMPANY | $93,392 |
| Jan 3, 2024 | CalSHAPE ProgramPlumbing & restrooms | — | — |
| Dec 26, 2023 | Districtwide SlurryPaving & streets | — | — |
| Dec 12, 2023 | Washington TK PlaygroundParks, landscape & fields | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.