24 public works projects registered with the California Department of Industrial Relations, 2018–2024 · Big Bear Lake. Reported contract value: $2,270,611.

Projects by year

YearProjectsReported contract value
20242$2,270,611
20236—
20224—
20215—
20202—
20192—
20183—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Water · 13
  • Other · 6
  • Solar, EV & energy · 2
  • Roofing · 1
  • Paving & streets · 1
  • Storm drain & flood control · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
PASO ROBLES TANK INC1$1,991,611
S PORTER INC1$279,000

Latest projects

DateProjectPrime contractorContract amount
Jul 24, 2024Wolf Reservoir Replacement ProjectStorm drain & flood controlPASO ROBLES TANK INC$1,991,611
May 29, 2024Pontell Hydropneumatic Tank InstallationRoofingS PORTER INC$279,000
Dec 31, 2023Garstin Operations BuildingSolar, EV & energy——
Dec 18, 2023Solar Division FieldSolar, EV & energy——
Jul 24, 2023Grout Creek Emergency Pipeline ReplacemeOther——
Jun 30, 2023Wolf Pipeline Replacement ProjectWater——
Jun 30, 20232023 Pipeline Replacement ProjectWater——
May 1, 2023Division No. 6 Well Site ImprovementsWater——
Aug 8, 20222022 Well Site Improvements - ConstructiWater——
Jul 5, 2022Moonridge Pipeline replacementOther——
Jun 6, 20222022 Well Site Improvements Project - LaWater——
Jun 6, 2022Division Well No. 9 Drilling ProjectWater——
Oct 1, 2021Wolf Reservoir, Booster, and Pipeline ReWater——
Sep 12, 20212022 Well Site Improvements - DesignWater——
Jul 12, 2021Division Well No. 9 Drilling & EquippingWater——
Jul 12, 20212022 Pipeline Replacement Project - DesiWater——
Apr 12, 20212018 USDA Pipeline Replacement Project -Other——
May 18, 20202018 USDA Pipeline Replacement Project -Other——
Apr 2, 2020Fawnskin Pipeline ExtensionPaving & streets——
Jun 17, 20192018 USDA Pipeline Replacement Project -Other——
Jan 1, 20192018 USDA Pipeline Replacement Project -Other——
Nov 30, 2018Division Well Field Solar ProjectWater——
Oct 30, 2018Sawmill Well Pumping PlantWater——
Sep 1, 2018Sawmill WellWater——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.