Los Angeles World Airports- Airports Development Group

18 public works projects registered with the California Department of Industrial Relations, 2015–2020 · Los Angeles.

Projects by year

YearProjectsReported contract value
20201—
20184—
20173—
20167—
20153—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 7
  • Buildings & facilities · 3
  • Demolition & site work · 2
  • Paving & streets · 2
  • Storm drain & flood control · 1
  • Sewer & wastewater · 1
  • Fire & life safety · 1
  • Water · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Latest projects

DateProjectPrime contractorContract amount
Sep 3, 2020Runway 25L Rehabilitation ProjectOther——
Sep 26, 2018Consolidated Rent-A-Car Center - CONRACBuildings & facilities——
Jun 1, 2018Airport Police FacilityBuildings & facilities——
Feb 1, 2018Automated People Mover - APMOther——
Jan 3, 2018CTA Security Bollards Phase 2Buildings & facilities——
Oct 2, 2017North Central Outfall Sewer Connection -Sewer & wastewater——
Sep 20, 2017Runway 25R Reconstruction ProjectOther——
Sep 1, 2017Taxiway T - Phase 2 ProjectOther——
Oct 14, 2016Terminal Cores & APM InterfaceDemolition & site work——
Sep 12, 2016Fire Life Safety System Replacement ProjFire & life safety——
Jun 7, 2016Imperial Cargo Complex Water Main ReplacWater——
Feb 15, 2016Runway 7L-25R Safety Area Improvements aPaving & streets——
Feb 15, 20167L-25R Safety Area Improvements and PavePaving & streets——
Jan 13, 2016TestOther——
Jan 10, 2016Qantas Hangar Demolition ProjectDemolition & site work——
Aug 5, 2015Runway 6R-24L Safety Area Improvements POther——
Apr 1, 2015Midfield Satellite Concourse North ConstOther——
Mar 9, 2015Runway 6L-24R Safety Area RehabilitationStorm drain & flood control——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.