Pacific Coast Fish, Wildlife and Wetlands Restoration Association
16 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Arcata, Humboldt County. Reported contract value: $3,551,102.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 1 | $292,385 |
| 2025 | 6 | $2,137,817 |
| 2024 | 4 | $1,120,900 |
| 2023 | 3 | — |
| 2016 | 1 | — |
| 2015 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 9
- Storm drain & flood control · 4
- Traffic & signals · 1
- Design, inspection & consulting · 1
- Buildings & facilities · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| Carmesin Construction, Inc. | 3 | $1,174,297 |
| PACIFIC WATERSHED ASSOCIATES, INC. | 3 | $967,268 |
| SARGENT EXCAVATION | 1 | $288,637 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jul 31, 2026 | Upper Savoy Cr. Salmonid Habitat DesignOther | PACIFIC WATERSHED ASSOCIATES, INC. | $292,385 |
| Sep 2, 2025 | LINDSAY CREEK (KRAMER/DALEY PROPERTY) INOther | Carmesin Construction, Inc. | $24,750 |
| Jul 31, 2025 | N.F. Mad R. Salmon Habitat Design ProjecDesign, inspection & consulting | PACIFIC WATERSHED ASSOCIATES, INC. | $345,622 |
| Jul 1, 2025 | Lindsay Cr. Off-Channel Habitat ProjectOther | SARGENT EXCAVATION | $288,637 |
| Jul 1, 2025 | Lower Little R. Coho Habitat ImprovementOther | Carmesin Construction, Inc. | $1,069,390 |
| Jul 1, 2025 | Lindsay Cr. Coho Passage ImprovementStorm drain & flood control | Carmesin Construction, Inc. | $80,157 |
| Jun 1, 2025 | South Fork Rowdy/Savoy Creeks Salmonid HTraffic & signals | PACIFIC WATERSHED ASSOCIATES, INC. | $329,261 |
| Sep 13, 2024 | Lindsay Creek Coho Barrier Removal ProjeStorm drain & flood control | — | $112,345 |
| Aug 28, 2024 | Ryan Creek Off-Channel Coho Habitat ImplBuildings & facilities | — | $407,475 |
| Aug 28, 2024 | Ryan Creek Off-Channel Coho Habitat ImplOther | — | $407,475 |
| Aug 1, 2024 | Tip Top Ridge Creek Coho Habitat ImproveOther | — | $193,605 |
| Oct 16, 2023 | Lower Little River Off-Channel Coho HabiOther | — | — |
| Oct 1, 2023 | Cider Mill Creek Coho Barrier Removal anOther | — | — |
| May 25, 2023 | Cider Mill Creek Coho Barrier Removal anOther | — | — |
| Sep 27, 2016 | Yontocket Slough Fish Passage ProjectStorm drain & flood control | — | — |
| Sep 16, 2015 | Nickerson Creek Tributaries No. 1 and NoStorm drain & flood control | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.