Antelope Valley East Kern Water Agency
67 public works projects registered with the California Department of Industrial Relations, 2012–2026 · Palmdale, Los Angeles County. Reported contract value: $6,654,020.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 1 | $298,000 |
| 2025 | 4 | $1,433,540 |
| 2024 | 8 | $4,922,480 |
| 2023 | 9 | — |
| 2022 | 5 | — |
| 2021 | 6 | — |
| 2020 | 11 | — |
| 2018 | 2 | — |
| 2017 | 3 | — |
| 2016 | 7 | — |
| 2015 | 2 | — |
| 2013 | 4 | — |
| 2012 | 3 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Water · 28
- Other · 24
- Buildings & facilities · 3
- Roofing · 3
- Paving & streets · 3
- Design, inspection & consulting · 2
- Sewer & wastewater · 2
- Electrical, low voltage & AV · 1
- Solar, EV & energy · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| PYRAMID BUILDING AND ENGINEERING INC | 1 | $630,500 |
| A N M CONSTRUCTION & ENGINEERING | 1 | $298,000 |
| ARCHIE FLOYD'S ROADRUNNER PUMP SERVICE | 1 | $125,000 |
| A V HERITAGE BUILDERS INC | 1 | $77,500 |
| F.D. THOMAS, INC. | 1 | $74,850 |
| ERS INDUSTRIAL SERVICES INC | 1 | $27,540 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Mar 11, 2026 | Asphalt MaintenanceWater | A N M CONSTRUCTION & ENGINEERING | $298,000 |
| Oct 29, 2025 | Quartz Hill Annual Channel CleaningWater | ERS INDUSTRIAL SERVICES INC | $27,540 |
| Sep 9, 2025 | Quartz Hill Clearwell No. 1 Valve ReplacOther | PYRAMID BUILDING AND ENGINEERING INC | $630,500 |
| Jul 8, 2025 | Admin Mechanical Equipment EnclosureRoofing | A V HERITAGE BUILDERS INC | $77,500 |
| Mar 28, 2025 | West Admin Roof ReplacementRoofing | — | $698,000 |
| Dec 9, 2024 | Mojave & Lake Hughes Feeder Valve ReplacOther | — | $651,430 |
| Nov 15, 2024 | EW24 Well Pump RepairWater | ARCHIE FLOYD'S ROADRUNNER PUMP SERVICE | $125,000 |
| Nov 13, 2024 | Chemical Tank Recoating ProjectOther | F.D. THOMAS, INC. | $74,850 |
| Oct 16, 2024 | Pipeline Condition AssessmentOther | — | $1,937,350 |
| Oct 16, 2024 | Leona Valley Tank RehabilitationWater | — | $1,937,350 |
| Sep 24, 2024 | HDWB Stoplog ModificationOther | — | $196,500 |
| Jun 5, 2024 | HDWB Well Drilling Package #3Water | — | — |
| Feb 3, 2024 | Annual QHWTP Debris RemovalOther | — | — |
| Sep 25, 2023 | Temporary Power for Aqueduct TurnoutWater | — | — |
| Mar 15, 2023 | EAFB Pump ConversionOther | — | — |
| Mar 15, 2023 | LV Feeder Valve Replacement/InstallOther | — | — |
| Mar 15, 2023 | PRID Line Replacement and TO RebuildOther | — | — |
| Mar 15, 2023 | QHWTP 4-inch Utility Line ReplacementOther | — | — |
| Mar 15, 2023 | NF Raise Manholes to GradeSewer & wastewater | — | — |
| Mar 15, 2023 | 75th Street Turnout RebuildPaving & streets | — | — |
| Mar 15, 2023 | Saddle Replacement on 10th Street/ValvePaving & streets | — | — |
| Jan 1, 2023 | Quartz Hill State Screen ConveyorOther | — | — |
| Aug 30, 2022 | Well EW-24 Wire RepairWater | — | — |
| Jul 1, 2022 | HDWB Stage 1 and Stage 2 Recharge SystemOther | — | — |
| Apr 1, 2022 | High Desert Water Bank Well Drilling PacWater | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.