Live Oak School District

30 public works projects registered with the California Department of Industrial Relations, 2012–2023 · Santa Cruz.

Projects by year

YearProjectsReported contract value
20233—
20223—
20212—
20204—
20192—
20171—
20162—
20152—
20141—
20132—
20125—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Solar, EV & energy · 7
  • Demolition & site work · 6
  • Buildings & facilities · 4
  • HVAC & mechanical · 2
  • Other · 2
  • Painting & flooring · 2
  • Parks, landscape & fields · 2
  • Roofing · 2
  • Electrical, low voltage & AV · 1
  • Paving & streets · 1
  • Plumbing & restrooms · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Latest projects

DateProjectPrime contractorContract amount
Oct 25, 2023Green Acres PlaygroundParks, landscape & fields——
May 31, 2023Office furniture/Cubicle assemblyOther——
Mar 31, 2023ADA improvements at all sitesDemolition & site work——
Jul 5, 2022LOSD DSA Shade CanopiesBuildings & facilities——
Jul 1, 2022Site Work at Shoreline Middle SchoolDemolition & site work——
Jun 13, 2022Re-Painting at Del Mar ElementaryPainting & flooring——
Sep 30, 2021Cubicle and office installation at the DOther——
Sep 24, 2021Shoreline Middle School Boiler ReplacemeHVAC & mechanical——
May 26, 2020Shoreline Middle School Solar Panel RepaSolar, EV & energy——
May 6, 2020Shoreline Middle School Solar Panel RepaSolar, EV & energy——
Apr 17, 2020Re-Roofing at Shoreline Middle SchoolRoofing——
Mar 18, 2020Shoreline Middle School Lighting ProjectElectrical, low voltage & AV——
Sep 30, 2019Green Acres Door ReplacementBuildings & facilities——
May 20, 2019Athletic Field Improvement at ShorelineParks, landscape & fields——
May 1, 2017Plastering & Repainting at LO ElementaryPainting & flooring——
Nov 22, 2016Energy Services AgreementHVAC & mechanical——
Jul 1, 2016Portable Removal at Live Oak ElementaryBuildings & facilities——
Jun 15, 2015Live Oak Elementary Restroom ModernizatiPlumbing & restrooms——
Mar 30, 2015New Boys & Girls Club at Shoreline MiddlBuildings & facilities——
Jul 28, 2014Soil Work for New Boys & Girls Club at SDemolition & site work——
Jun 17, 2013Del Mar ElementaryDemolition & site work——
Jun 17, 2013Green Acres ElementaryDemolition & site work——
Jul 23, 2012solar various sites, ga es, lo es, oceanSolar, EV & energy——
Jul 23, 2012solar various sites, ga es, lo es, oceanSolar, EV & energy——
Jul 23, 2012solar various sites, ga es, lo es, oceanSolar, EV & energy——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.

Do you bid public works?

Find your license and claim your free Atriam profile. It lists the public works projects registered under your license.

Find my license