16 public works projects registered with the California Department of Industrial Relations, 2023–2026 · Newark, Alameda County. Reported contract value: $7,165,154.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 4 | $4,421,129 |
| 2025 | 3 | $822,035 |
| 2024 | 2 | $1,921,991 |
| 2023 | 7 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Paving & streets · 12
- Parks, landscape & fields · 1
- Other · 1
- Buildings & facilities · 1
- Storm drain & flood control · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| G BORTOLOTTO & COMPANY | 2 | $3,638,129 |
| VILLALOBOS & ASSOCIATES | 2 | $1,443,300 |
| GRAYMAR ENVIRONMENTAL SERVICES LLC | 1 | $103,635 |
| PRECISION CONCRETE CUTTING | 1 | $49,500 |
| KIER & WRIGHT CIVIL ENGINEERS AND SURVEY | 1 | $8,600 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jul 13, 2026 | Citywide Sidewalk GrindingPaving & streets | PRECISION CONCRETE CUTTING | $49,500 |
| Jun 25, 2026 | FY2026 ANNUAL AC OVERLAY (PHASE 2)Paving & streets | G BORTOLOTTO & COMPANY | $949,441 |
| May 28, 2026 | FY2026 ANNUAL AC STREET OVERLAY (PHASE 1Paving & streets | G BORTOLOTTO & COMPANY | $2,688,688 |
| Jan 22, 2026 | 2026 Concrete Projects (CGSW & Ped Ramp)Paving & streets | VILLALOBOS & ASSOCIATES | $733,500 |
| Nov 18, 2025 | Underground Fuel Storage Tank Rem & DispOther | GRAYMAR ENVIRONMENTAL SERVICES LLC | $103,635 |
| Jul 24, 2025 | 2025 Concrete Projects (CGSW & Ped Ramp)Paving & streets | VILLALOBOS & ASSOCIATES | $709,800 |
| Feb 19, 2025 | Mowry Avenue - Partial TopoBuildings & facilities | KIER & WRIGHT CIVIL ENGINEERS AND SURVEY | $8,600 |
| Jul 25, 2024 | 2024 STREET SLURRY SEAL PRGM, PROJ1345Paving & streets | — | $422,000 |
| Jun 27, 2024 | '24 AC Overlay, Project 1344Paving & streets | — | $1,499,991 |
| Aug 9, 2023 | Smith Avenue Sink Hole RepairsStorm drain & flood control | — | — |
| Jul 5, 2023 | FY 2022-2023 Rubberized Cape Seal and SlPaving & streets | — | — |
| Jun 12, 2023 | Cherry Street Class IV Separated BikewayPaving & streets | — | — |
| Jun 5, 2023 | Safe Routes to School ImprovementsPaving & streets | — | — |
| May 29, 2023 | 2022-2023 Asphalt Concrete Street OverlaPaving & streets | — | — |
| May 29, 2023 | 2022-2023 Asphalt Concrete Street OverlaPaving & streets | — | — |
| May 15, 2023 | FY 2021-2022 Citywide Park Pathways forParks, landscape & fields | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.