14 public works projects registered with the California Department of Industrial Relations, 2016–2026 · Long Beach, Los Angeles County. Reported contract value: $13,980,408.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 3 | $12,030,147 |
| 2025 | 4 | $1,700,727 |
| 2024 | 4 | $106,077 |
| 2020 | 1 | — |
| 2016 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 5
- Roofing · 2
- Other · 2
- Demolition & site work · 1
- Design, inspection & consulting · 1
- HVAC & mechanical · 1
- Elevators & conveying · 1
- Paving & streets · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| DEWBERRY DESIGN - BUILDERS INC | 5 | $150,166 |
| BNBUILDERS, INC. | 1 | $12,000,000 |
| ATHENA ENGINEERING, INC. | 1 | $1,535,574 |
| HARRY H JOH CONSTRUCTION INC | 1 | $143,457 |
| Pacific Industrial Electric | 1 | $50,000 |
| MIK CONSTRUCTION INC | 1 | $19,212 |
| VINCOR CONSTRUCTION INC | 1 | $10,935 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 30, 2026 | New Automatic Door OpenerBuildings & facilities | MIK CONSTRUCTION INC | $19,212 |
| Jun 10, 2026 | CSUCO - SW Dumke Roof LeakRoofing | VINCOR CONSTRUCTION INC | $10,935 |
| May 7, 2026 | World Trade Center TI ProjectBuildings & facilities | BNBUILDERS, INC. | $12,000,000 |
| Dec 8, 2025 | Lobby Skylight Leak Repair ProjectBuildings & facilities | DEWBERRY DESIGN - BUILDERS INC | $80,865 |
| Aug 13, 2025 | AHU Renewal ProjectHVAC & mechanical | ATHENA ENGINEERING, INC. | $1,535,574 |
| Mar 17, 2025 | CSUCO Elevator Battery Stand-By PowerElevators & conveying | Pacific Industrial Electric | $50,000 |
| Feb 6, 2025 | CSUCO Shade Panel RepairBuildings & facilities | DEWBERRY DESIGN - BUILDERS INC | $34,289 |
| Oct 18, 2024 | Water Barricades November BOTOther | DEWBERRY DESIGN - BUILDERS INC | $10,551 |
| Sep 19, 2024 | CSUCO - Water Barricades for Sept BOTOther | DEWBERRY DESIGN - BUILDERS INC | $10,551 |
| Aug 5, 2024 | CSUCO - Restriping South Parking LotPaving & streets | DEWBERRY DESIGN - BUILDERS INC | $13,910 |
| Jul 1, 2024 | CSUCO - Phase 2 - MMS First Floor FiberDemolition & site work | — | $71,065 |
| Nov 4, 2020 | Maritime Academy WalkwayDesign, inspection & consulting | — | — |
| Sep 22, 2016 | TI - Catalina Landing Building 310Buildings & facilities | — | — |
| — | CO Roof Fall ProtectionRoofing | HARRY H JOH CONSTRUCTION INC | $143,457 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.