7 public works projects registered with the California Department of Industrial Relations, 2024–2026 · Wasco, Kern County. Reported contract value: $12,307,572.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 3 | $11,706,091 |
| 2025 | 3 | $503,481 |
| 2024 | 1 | $98,000 |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 2
- Demolition & site work · 2
- Parks, landscape & fields · 1
- Paving & streets · 1
- Storm drain & flood control · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| W M LYLES CO | 2 | $8,990,548 |
| LONNIE A CROSS LAND LEVELING INC | 2 | $493,400 |
| SPECIALTY CONSTRUCTION, INC. | 1 | $2,431,543 |
| S&B SONS INC | 1 | $352,081 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Sep 14, 2026 | Dresser Recharge Structures and PipelineDemolition & site work | W M LYLES CO | $8,892,548 |
| May 14, 2026 | Pipeline Relocation ProjectOther | SPECIALTY CONSTRUCTION, INC. | $2,431,543 |
| Feb 12, 2026 | Southeast Recharge Grading ProjectDemolition & site work | LONNIE A CROSS LAND LEVELING INC | $382,000 |
| Oct 13, 2025 | Southeast Recharge PipelineParks, landscape & fields | S&B SONS INC | $352,081 |
| May 30, 2025 | Kimberlina Recharge PondsStorm drain & flood control | LONNIE A CROSS LAND LEVELING INC | $111,400 |
| Feb 26, 2025 | 7th Street Pipeline RepairPaving & streets | — | $40,000 |
| Jul 29, 2024 | Dresser RechargeOther | W M LYLES CO | $98,000 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.