Solano Community College District
336 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Fairfield, Solano County. Reported contract value: $23,623,357.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 3 | $10,149,396 |
| 2025 | 11 | $10,403,412 |
| 2024 | 20 | $3,070,549 |
| 2023 | 20 | — |
| 2022 | 20 | — |
| 2021 | 22 | — |
| 2020 | 18 | — |
| 2019 | 12 | — |
| 2018 | 14 | — |
| 2017 | 65 | — |
| 2016 | 55 | — |
| 2015 | 75 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 105
- Other · 58
- HVAC & mechanical · 33
- Electrical, low voltage & AV · 32
- Design, inspection & consulting · 17
- Fire & life safety · 14
- Roofing · 14
- Parks, landscape & fields · 13
- Paving & streets · 11
- Painting & flooring · 10
- Plumbing & restrooms · 8
- Demolition & site work · 6
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| RESTORATION MANAGEMENT COMPANY | 2 | $70,000 |
| DOWDLE & SONS MECHANICAL INC | 1 | $9,622,700 |
| E F BRETT & COMPANY INC | 1 | $6,660,000 |
| ARTHULIA INC. | 1 | $1,210,000 |
| MATRIX HG INC | 1 | $811,542 |
| ALCAL SPECIALTY CONTRACTING INC | 1 | $700,000 |
| WESTEK BUILDERS | 1 | $467,579 |
| AIR & LUBE SYSTEMS INC | 1 | $311,253 |
| P B ELECTRIC INC | 1 | $259,220 |
| KYA SERVICES LLC | 1 | $152,887 |
| LISTER CONSTRUCTION INC | 1 | $59,117 |
| NET ELECTRIC INC | 1 | $43,146 |
| NEIL O ANDERSON AND ASSOCIATES INC | 1 | $25,780 |
| STERIS CORPORATION | 1 | $22,553 |
| ROBERTSON INDUSTRIES INC | 1 | $16,521 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| May 18, 2026 | Building 1400 lighting upgrade projectElectrical, low voltage & AV | WESTEK BUILDERS | $467,579 |
| Apr 15, 2026 | Asphalt Replacement ProjectPaving & streets | LISTER CONSTRUCTION INC | $59,117 |
| Apr 15, 2026 | HYDRONIC SYSTEM MODERNIZATIONBuildings & facilities | DOWDLE & SONS MECHANICAL INC | $9,622,700 |
| Sep 16, 2025 | Gas Leak Excavation and BackfillDemolition & site work | P B ELECTRIC INC | $259,220 |
| Aug 1, 2025 | Fairfield Sand Volleyball Courts ProjectOther | ARTHULIA INC. | $1,210,000 |
| Jul 16, 2025 | Baseball Field Drainage Improvement ProjStorm drain & flood control | KYA SERVICES LLC | $152,887 |
| May 15, 2025 | Hydronic Vault repair ProjectBuildings & facilities | — | $811,542 |
| Apr 23, 2025 | Totsurf safety surfacing for childcareParks, landscape & fields | ROBERTSON INDUSTRIES INC | $16,521 |
| Apr 16, 2025 | Hydronic Loop - B300 & 1200 Vault RepairBuildings & facilities | MATRIX HG INC | $811,542 |
| Mar 19, 2025 | VJ Autotech Vehicule Exhaust System DynoOther | AIR & LUBE SYSTEMS INC | $311,253 |
| Mar 17, 2025 | Shade Structures and Sandbox projectBuildings & facilities | — | $107,800 |
| Feb 19, 2025 | Shade Structure Replacement NB251031Buildings & facilities | NEIL O ANDERSON AND ASSOCIATES INC | $25,780 |
| Feb 5, 2025 | New concrete walkway for ELCConcrete & masonry | — | $36,867 |
| Jan 15, 2025 | Building 1600 Modernization ProjectBuildings & facilities | E F BRETT & COMPANY INC | $6,660,000 |
| Oct 31, 2024 | Building 1400 Roof leak ProjectRoofing | RESTORATION MANAGEMENT COMPANY— | $30,000 |
| Oct 24, 2024 | Building 900 Heating Hot Water LeakHVAC & mechanical | RESTORATION MANAGEMENT COMPANY | $40,000 |
| Oct 2, 2024 | Building 800 EMT and Nursing RenovationBuildings & facilities | — | $229,849 |
| Aug 26, 2024 | Building 1400 modernization Roof Phase 1Roofing | ALCAL SPECIALTY CONTRACTING INC | $700,000 |
| Aug 22, 2024 | B1400 Modernization (Ph 1) Door ProjectElectrical, low voltage & AV | — | $330,000 |
| Aug 21, 2024 | B1400 Modernization Roof ProjectRoofing | — | $700,000 |
| Aug 12, 2024 | vandalism/ wire theft light polesElectrical, low voltage & AV | NET ELECTRIC INC | $43,146 |
| Aug 6, 2024 | Preventative Generator Maintenance VVElectrical, low voltage & AV | STERIS CORPORATION | $22,553 |
| Jul 18, 2024 | Campus Wide Interior Refresh (Phase 1B)Plumbing & restrooms | — | $975,000 |
| Jun 3, 2024 | CAMPUS WIDE INTERIOR REFRESH PHASE 1 PROPlumbing & restrooms | — | — |
| May 23, 2024 | Vacaville Water Intrusion ProjectBuildings & facilities | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.