San Bernardino Valley Water Conservation District

25 public works projects registered with the California Department of Industrial Relations, 2017–2026 · Redlands. Reported contract value: $343,624.

Projects by year

YearProjectsReported contract value
20261$20,000
20242$323,624
20239—
20227—
20202—
20171—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 19
  • Paving & streets · 2
  • Design, inspection & consulting · 1
  • Sewer & wastewater · 1
  • Electrical, low voltage & AV · 1
  • Storm drain & flood control · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
LARRY JACINTO CONSTRUCTION INC2$323,624
WESTLAND GROUP INC1$20,000

Latest projects

DateProjectPrime contractorContract amount
Jul 7, 2026Mill Creek N. Canal Sensor MappingDesign, inspection & consultingWESTLAND GROUP INC$20,000
Jul 15, 2024Santa Ana River RPU Vegetation ClearingOtherLARRY JACINTO CONSTRUCTION INC$3,020
May 15, 2024Santa Ana Spreading Basin MaintenanceOtherLARRY JACINTO CONSTRUCTION INC$320,604
Dec 18, 2023Softplug Adjustment Mill CreekOther——
Dec 5, 2023Mill Creek West of Basin 22 ClearingPaving & streets——
Dec 5, 2023Mill Creek Basin 14 & 15 Berm RepairOther——
Sep 28, 2023Softplug Replacement Mill CreekStorm drain & flood control——
Sep 20, 2023Mentone Property-Septic SystemSewer & wastewater——
Aug 14, 2023Santa Ana Spreading Basin MaintenanceOther——
Aug 8, 2023Softplug Adjustment Mill CreekOther——
Aug 1, 2023Mill Creek Diversion and Debris ManagemeOther——
Aug 1, 2023Mill Creek Diversion and Debris ManagemeOther——
Apr 21, 2022Mentone Shop ImprovementElectrical, low voltage & AV——
Mar 15, 2022Mill, Bledsoe, and Cook Creek PreliminarOther——
Mar 15, 2022Mill, Bledsoe, and Cook Creek PreliminarOther——
Feb 15, 2022Plunge and Oak Creek Diversions and BasiOther——
Feb 2, 2022Plunge and Oak Creek Diversions and BasiOther——
Feb 1, 2022Waterman, Lynwood Basins and Twin CreekOther——
Jan 19, 2022Waterman, Lynwood Basins and Twin CreekOther——
Aug 3, 2020Plunge Creek Conservation ProjectOther——
Jul 15, 2020Plunge Creek Conservation ProjectOther——
Dec 25, 2017Redlands Plaza parking lot and sidewalkPaving & streets——
—Mill Creek Diversion and Debris ManagemeOther——
—Mill Creek Diversion and Debris ManagemeOther——
—Mill Creek Diversion and Debris ManagemeOther——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.