193 public works projects registered with the California Department of Industrial Relations, 2014–2026 · Redlands, San Bernardino County. Reported contract value: $59,225,470.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 5 | $14,103,531 |
| 2025 | 23 | $22,089,372 |
| 2024 | 21 | $23,032,568 |
| 2023 | 13 | — |
| 2022 | 20 | — |
| 2021 | 11 | — |
| 2020 | 14 | — |
| 2019 | 10 | — |
| 2018 | 19 | — |
| 2017 | 12 | — |
| 2016 | 25 | — |
| 2015 | 14 | — |
| 2014 | 3 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Paving & streets · 41
- Sewer & wastewater · 30
- Water · 29
- Other · 26
- Traffic & signals · 19
- Buildings & facilities · 15
- Parks, landscape & fields · 13
- Storm drain & flood control · 6
- Electrical, low voltage & AV · 4
- Design, inspection & consulting · 3
- HVAC & mechanical · 3
- Plumbing & restrooms · 2
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| TRYCO GENERAL ENGINEERING | 5 | $4,398,761 |
| METROCELL CONSTRUCTION INC | 3 | $1,557,605 |
| MCC PIPELINE INC | 2 | $16,061,958 |
| BEADOR CONSTRUCTION COMPANY INC | 1 | $5,573,700 |
| ELEGANT CONSTRUCTION INC | 1 | $3,097,000 |
| ONYX PAVING COMPANY INC | 1 | $669,000 |
| ANGELUS WATERPROOFING AND RESTORATION INC | 1 | $648,548 |
| Q&E PIPELINE COMPANY | 1 | $629,664 |
| B-81 PAVING INC | 1 | $600,000 |
| GARCON CONSTRUCTION INC | 1 | $529,406 |
| GENERAL PUMP COMPANY INC | 1 | $500,000 |
| R & J CONSTRUCTION LLC | 1 | $449,236 |
| RINCON CONSULTANTS, INC. | 1 | $369,750 |
| MORAL BUILDERS | 1 | $299,828 |
| LIFTECH ELEVATOR SERVICES LLC | 1 | $251,000 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jul 21, 2026 | California St/Redlands Blvd IntersectionStorm drain & flood control | BEADOR CONSTRUCTION COMPANY INC | $5,573,700 |
| Jul 21, 2026 | On-Call Pavement Repair-Water FacilitiesTraffic & signals | B-81 PAVING INC | $600,000 |
| Apr 7, 2026 | WWTP Hillside Stabilization and StairwaySewer & wastewater | R & J CONSTRUCTION LLC | $449,236 |
| Mar 3, 2026 | Water Facilities GeneratorsWater | — | $3,477,000 |
| Feb 17, 2026 | 2025 CIP Water Pipeline ReplacementWater | MCC PIPELINE INC | $4,003,595 |
| Dec 16, 2025 | PMP 2025 Street Resurfacing ProjectPaving & streets | — | $5,566,094 |
| Nov 18, 2025 | Cypress Ave and Cajon St Traffic SignalTraffic & signals | — | $730,281 |
| Nov 4, 2025 | WELL & BOOSTER PUMP ON-CALL AND MAINTENAWater | GENERAL PUMP COMPANY INC | $500,000 |
| Oct 21, 2025 | WWTP Hillside Stabilization and StairwaySewer & wastewater | MORAL BUILDERS | $299,828 |
| Oct 21, 2025 | Joint Utilities Laboratory Building RenoBuildings & facilities | ELEGANT CONSTRUCTION INC | $3,097,000 |
| Oct 7, 2025 | Palo Alto Storm Drain ImprovementStorm drain & flood control | METROCELL CONSTRUCTION INC | $83,094 |
| Sep 23, 2025 | Mobile OfficeSewer & wastewater | MCGRATH RENTCORP | $123,403 |
| Sep 16, 2025 | 2025 Alley Paving Improvement ProjectPaving & streets | — | $465,000 |
| Sep 2, 2025 | 2025 CIP Sewer Pipeline Replacement ProjSewer & wastewater | TRYCO GENERAL ENGINEERING | $1,494,516 |
| Sep 2, 2025 | 2025 Sidewalk & ADA Ramp ReplacementPaving & streets | GARCON CONSTRUCTION INC | $529,406 |
| Sep 2, 2025 | Landfill Leachate Environmental Site AssSewer & wastewater | RINCON CONSULTANTS, INC. | $369,750 |
| May 6, 2025 | HSIP Cycle 10 Enhanced CrosswalkTraffic & signals | ELECNOR BELCO ELECTRIC INC | $248,067 |
| May 6, 2025 | Orange Blossom Trail Phase 4Storm drain & flood control | TRYCO GENERAL ENGINEERING | $960,145 |
| May 6, 2025 | On-Call Sewer Collection System MaintenaSewer & wastewater | HOUSTON & HARRIS P C S INC | $250,000 |
| May 6, 2025 | Citrus Ave Parking Structure MaintenanceTraffic & signals | ANGELUS WATERPROOFING AND RESTORATION INC | $648,548 |
| May 6, 2025 | Orange Blossom Trail Phase 4Storm drain & flood control | TRYCO GENERAL ENGINEERING | $960,145 |
| May 6, 2025 | Ford Park Restroom Building ReplacementPlumbing & restrooms | METROCELL CONSTRUCTION INC | $850,600 |
| Apr 15, 2025 | A.K. Smiley Public Library Lower LevelElevators & conveying | LIFTECH ELEVATOR SERVICES LLC | $251,000 |
| Mar 4, 2025 | Recycled Water for California St OrangeWater | Q&E PIPELINE COMPANY | $629,664 |
| Mar 4, 2025 | 2025 Citywide Pavement Repair ProjectPaving & streets | ONYX PAVING COMPANY INC | $669,000 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.
Do you bid public works?
Find your license and claim your free Atriam profile. It lists the public works projects registered under your license.