Brian Barr
19 public works projects registered with the California Department of Industrial Relations, 2018–2025 · Fresno, Fresno County. Reported contract value: $248,778.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2025 | 3 | $32,740 |
| 2024 | 9 | $216,038 |
| 2021 | 1 | — |
| 2020 | 1 | — |
| 2019 | 3 | — |
| 2018 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 5
- Buildings & facilities · 4
- Demolition & site work · 3
- HVAC & mechanical · 2
- Roofing · 1
- Concrete & masonry · 1
- Design, inspection & consulting · 1
- Sewer & wastewater · 1
- Storm drain & flood control · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| Pierce Crane Inc | 2 | $1,800 |
| PROVOST & PRITCHARD ENGINEERING GROUP, INC | 1 | $132,500 |
| NATIONS ROOF WEST LLC | 1 | $24,525 |
| SOUND CONTRACTING INC | 1 | $20,348 |
| PARC ENVIRONMENTAL | 1 | $17,600 |
| MESA ENERGY SYSTEMS INC | 1 | $16,105 |
| PUMA CONSTRUCTION & RESTORATION CO | 1 | $10,855 |
| TROY DUDLEY | 1 | $8,800 |
| OMEGA AIR AND HEATING INC | 1 | $8,000 |
| JOHNSON CONTROLS FIRE PROTECTION LP | 1 | $4,285 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| May 14, 2025 | Fresno City Hall Push Button InstallBuildings & facilities | JOHNSON CONTROLS FIRE PROTECTION LP | $4,285 |
| Feb 21, 2025 | 1249 Van Ness Asbestos AbatementDemolition & site work | PARC ENVIRONMENTAL | $17,600 |
| Feb 18, 2025 | Block Wall RepairConcrete & masonry | PUMA CONSTRUCTION & RESTORATION CO | $10,855 |
| Dec 9, 2024 | Tower Theater Plaster RepairOther | TROY DUDLEY | $8,800 |
| Dec 2, 2024 | Tower Theater AbatementDemolition & site work | — | $3,960 |
| Nov 18, 2024 | City Hall SoundproofingBuildings & facilities | SOUND CONTRACTING INC | $20,348 |
| Oct 31, 2024 | Tower Theatre AC ReplacementHVAC & mechanical | MESA ENERGY SYSTEMS INC | $16,105 |
| Oct 23, 2024 | Romain Condenser ReplacementOther | Pierce Crane Inc | $800 |
| Oct 23, 2024 | Sequoia Roof RepairsRoofing | NATIONS ROOF WEST LLC | $24,525 |
| Oct 4, 2024 | Building T Evap ReplacementBuildings & facilities | Pierce Crane Inc | $1,000 |
| Sep 20, 2024 | Building W Evap ReplacementBuildings & facilities | OMEGA AIR AND HEATING INC | $8,000 |
| Sep 16, 2024 | Santa Fe Depot Consulting & DesignDesign, inspection & consulting | PROVOST & PRITCHARD ENGINEERING GROUP, INC— | $132,500 |
| Jan 31, 2021 | Pacific Inn Termite AbatementDemolition & site work | — | — |
| Feb 4, 2020 | ROC - Belfor Clean Up Feb 2020Sewer & wastewater | — | — |
| Oct 7, 2019 | 5 year Fire InspectionsOther | — | — |
| Jul 1, 2019 | Quarterly Inspections for COB2 AutomatioOther | — | — |
| Jul 1, 2019 | Quarterly Inspections for COB2 AutomatioOther | — | — |
| Nov 22, 2018 | Child Care Center RestorationStorm drain & flood control | — | — |
| May 21, 2018 | Burner Replacement - HOJHVAC & mechanical | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.