MIDSTATE BARRIER INC
California contractor license #529261 · Stockton, San Joaquin County
License
- License number
- 529261
- Status
- Clear
- Classifications
- A General Engineering Contractor
- HAZ Hazardous Substance Removal Certification
- Business type
- Corporation
- Issued
- May 2, 1988
- Expires
- May 31, 2028
- Workers' compensation
- Workers' Compensation Insurance — Old Republic Insurance Company
- Contractor's bond
- $25,000 — Western Surety Company
- DIR public works registration
- Registered through Jun 30, 2027
From the California Contractors State License Board (CSLB) public license file, last updated Jun 1, 2026. Verify license #529261 on CSLB's License Check.
California public works
MIDSTATE BARRIER INC appears on 180 public works projects registered with the California Department of Industrial Relations, 23 of them as the prime contractor, for 86 awarding bodies between 2012 and 2026. Projects it led total $43,147,660 in reported contract value.
| Date | Project | Awarding body | Role | Contract amount |
|---|---|---|---|---|
| Nov 17, 2026 | 06-Mad-99-0.1/8.1Other | California Department of Transportation (Caltrans) | Subcontractor | $77,277,277 |
| Sep 23, 2026 | 06-Mad-41-23.5Electrical, low voltage & AV | California Department of Transportation (Caltrans) | Subcontractor | $2,449,111 |
| Sep 15, 2026 | 2026 Annual Guardrail Repair, RDS 26-12Traffic & signals | Napa County Public Works | Prime | $367,903 |
| Sep 1, 2026 | Liberty Road and Sowles Road ResurfacingTraffic & signals | San Joaquin County Public Works | Subcontractor | $1,640,000 |
| Aug 21, 2026 | 05-Mon-101-77.0/84.5Other | California Department of Transportation (Caltrans) | Subcontractor | $3,817,170 |
| Jul 27, 2026 | Socrates Mine RD Slide RepairsTraffic & signals | County of Lake Department of Public Works | Subcontractor | $1,834,681 |
| Jul 16, 2026 | Parlier Guardrail ImprovementsTraffic & signals | City of Parlier_ | Prime | $122,800 |
| Jul 14, 2026 | Deer Valley Rd Traffic safety ImprovemenTraffic & signals | Contra Costa County Public Works Department | Subcontractor | $549,142 |
| Jul 7, 2026 | Countywide Guardrail Upgrades Phase IITraffic & signals | Contra Costa County Public Works Department | Prime | $1,428,778 |
| Jun 25, 2026 | 03-ED,Nev,Pla,Sac,Sut-50,70,80,89,99,267Other | California Department of Transportation (Caltrans) | Subcontractor | $780,200 |
| Jun 23, 2026 | Central Expressway Pavement RehabPaving & streets | County of Santa Clara, Roads and Airports Dept. | Subcontractor | $7,975,728 |
| Jun 17, 2026 | Winter Storms 2024-2025 damaged site-WohStorm drain & flood control | County of Sonoma – SPI _ Sonoma Public Infrastructure | Subcontractor | $2,851,390 |
| Jun 2, 2026 | Minor B - Construction of new concrete bConcrete & masonry | Department of Transportation, Division of Procurement and Contracts | Prime | $73,737 |
| May 19, 2026 | EXPRESSWAY GUARDRAIL REPLACEMENT AND SAFTraffic & signals | County of Santa Clara, Roads and Airports Dept. | Subcontractor | $2,120,713 |
| May 15, 2026 | 2026 PPP - Seals and Overlays ProjectStorm drain & flood control | County of Sonoma – SPI _ Sonoma Public Infrastructure | Subcontractor | $5,699,812 |
| Apr 30, 2026 | SB Minor B- 06A3312Traffic & signals | California Department of Transportation (Caltrans) | Subcontractor | $259,989 |
| Apr 27, 2026 | 2026 Road Paving ProjectPaving & streets | City of Lafayette | Subcontractor | $3,176,685 |
| Apr 14, 2026 | Red Fox Creek BridgeBridges & structures | County of Santa Clara, Roads and Airports Dept. | Subcontractor | $2,970,329 |
| Apr 14, 2026 | Rossi Bridge Phase 2, RDS 25-25BBridges & structures | Napa County Public Works | Subcontractor | $1,470,376 |
| Apr 7, 2026 | Placer Parkway Phase 1Bridges & structures | County of Placer - Department of Public Works | Subcontractor | $61,648,965 |
| Mar 27, 2026 | EFA - 04A7597Bridges & structures | California Department of Transportation | Prime | $196,000 |
| Mar 24, 2026 | Plymouth Avenue GuardrailTraffic & signals | City of Corcoran | Prime | $176,176 |
| Mar 17, 2026 | 06A3308Traffic & signals | California Department of Transportation (Caltrans) | Prime | $260,000 |
| Feb 20, 2026 | 05-Mon-68-0.3/15.7Storm drain & flood control | California Department of Transportation (Caltrans) | Subcontractor | $9,649,350 |
| Jan 28, 2026 | New Hope Road Bridge at Grizzly Slough RBridges & structures | County of Sacramento | Subcontractor | $4,536,070 |
Most recent 25 of 180. Contract amounts are the whole project's, as the awarding body reported them to DIR (reported since July 2024); a role is "Prime" when the awarding body registered the contractor on the project.
Awarding bodies it works for most
- California Department of Transportation (Caltrans) · 36 projects
- County of Santa Clara, Roads and Airports Dept. · 8 projects
- County of Sonoma – SPI _ Sonoma Public Infrastructure · 8 projects
- Napa County Public Works · 8 projects
- CITY OF STOCKTON - PUBLIC WORKS · 7 projects
- Contra Costa County Public Works Department · 4 projects
- Department of Transportation, Division of Procurement and Contracts · 4 projects
- San Joaquin County Public Works · 4 projects
- County of Monterey Public Works, Facilities and Parks · 3 projects
- County of Marin Department of Public Works · 3 projects
Is this your business?
Claim it on Atriam to add your work photos, service area and a booking link, and to run calls, leads, estimates and invoices in one place — free.