CALIFORNIA BARRICADE RENTALS INC
California contractor license #785733 · Santa Ana, Orange County
License
- License number
- 785733
- Status
- Clear
- Classifications
- C-31 Construction Zone Traffic Control Contractor
- Business type
- Corporation
- Issued
- Oct 12, 2000
- Expires
- Oct 31, 2028
- Workers' compensation
- Workers' Compensation Insurance — State Compensation Insurance Fund
- Contractor's bond
- $25,000 — American Contractors Indemnity Company
- DIR public works registration
- Registered through Jun 30, 2029
From the California Contractors State License Board (CSLB) public license file, last updated Sep 24, 2026. Verify license #785733 on CSLB's License Check.
California public works
CALIFORNIA BARRICADE RENTALS INC appears on 82 public works projects registered with the California Department of Industrial Relations, 2 of them as the prime contractor, for 49 awarding bodies between 2013 and 2026. Projects it led total $1,574,900 in reported contract value.
| Date | Project | Awarding body | Role | Contract amount |
|---|---|---|---|---|
| Jul 13, 2026 | FY 26/27 IRWD Traffic Control ServicesTraffic & signals | Irvine Ranch Water District 3 | Prime | $1,500,000 |
| Jul 1, 2026 | FY 26/27 IRWD Traffic Control ServicesTraffic & signals | Irvine Ranch Water District 3 | Subcontractor | $350,000 |
| Jun 22, 2026 | 346 Harbor Overflow AdditionSewer & wastewater | Costa Mesa Sanitary District - CMSD | Subcontractor | $470,000 |
| Jun 1, 2026 | YLWDPO13828Paving & streets | Yorba Linda Water District - Operations | Subcontractor | $65,777 |
| May 14, 2026 | Kellogg Dr Water and Sewer RplcmntSewer & wastewater | Yorba Linda Water District | Subcontractor | $1,265,000 |
| Mar 10, 2026 | Manchester and Prairie Lot Phase 1 ProjPaving & streets | City of Inglewood - Public Works | Subcontractor | $948,337 |
| Mar 2, 2026 | La Crescenta Green Impr - GeotechWater | County of Los Angeles Department of Public Works | Subcontractor | $44,600 |
| Jan 26, 2026 | Annual Local Paving ProgramPaving & streets | City of Seal Beach | Subcontractor | $600,000 |
| Sep 2, 2025 | University DrivePaving & streets | City of Carson | Subcontractor | $230,263 |
| Aug 14, 2025 | Bellevue & Delano Park Gas Probe RepairParks, landscape & fields | City of Los Angeles, Department of Recreation and Parks | Subcontractor | $34,223 |
| Jul 2, 2025 | Cerritos Sanitary Sewer ProjectSewer & wastewater | City of Anaheim | Subcontractor | $323,920 |
| Jul 1, 2025 | SCPA: FY 25-26Traffic & signals | Irvine Ranch Water District 3 | Subcontractor | $1,500,000 |
| May 29, 2025 | Strathern Park West surveysParks, landscape & fields | City of Los Angeles, Department of Recreation and Parks | Subcontractor | $40,377 |
| May 22, 2025 | PR 11123 & 11850Sewer & wastewater | Irvine Ranch Water District 3 | Subcontractor | $4,716,298 |
| May 12, 2025 | CDFA BLYTHE BORDER PROTECTION STATIONOther | State of CA, Department of General Service | Subcontractor | $262,000 |
| May 6, 2025 | Anita Lift Station & Stairs ReconstructSewer & wastewater | City of Laguna Beach | Subcontractor | $5,311,250 |
| Mar 25, 2025 | Sewer Pipeline CleaningSewer & wastewater | Emerald Bay Service District | Subcontractor | $2,500 |
| Feb 26, 2025 | Bay Bridge Pump Station ReplacementBridges & structures | Orange County Sanitation District | Subcontractor | $87,321,000 |
| Feb 20, 2025 | LANDSCAPE RENOVATION AND PLANTINGParks, landscape & fields | City of Irvine | Subcontractor | $18,266 |
| Feb 11, 2025 | Airfield Gate Security Project at MeadowElectrical, low voltage & AV | County of Kern - Public Works | Subcontractor | $856,118 |
| Feb 6, 2025 | Peninsula Verde Drive Percolation TestinOther | City of Rancho Palos Verdes | Subcontractor | $26,858 |
| Jan 14, 2025 | Interconnection Valve MaintenanceOther | City of Manhattan Beach | Subcontractor | $2,703 |
| Dec 17, 2024 | Lake County Sheriff's Administration FacBuildings & facilities | Lake County Public Services | Subcontractor | $11,965,000 |
| Dec 4, 2024 | On-Call Material Testing and Special InsDesign, inspection & consulting | City of Corona - 01 | Subcontractor | $250,000 |
| Nov 25, 2024 | Traffic ControlTraffic & signals | City of Manhattan Beach | Prime | $74,900 |
Most recent 25 of 82. Contract amounts are the whole project's, as the awarding body reported them to DIR (reported since July 2024); a role is "Prime" when the awarding body registered the contractor on the project.
Awarding bodies it works for most
- Irvine Ranch Water District 3 · 9 projects
- County of Los Angeles Department of Public Works · 5 projects
- Department of Toxic Substances Control · 5 projects
- City of Los Angeles, Department of Recreation and Parks · 4 projects
- Sanitation Districts of Los Angeles County · 4 projects
- City of Santa Ana · 4 projects
- City of Irvine · 3 projects
- City of Rancho Palos Verdes · 2 projects
- City of Corona - 01 · 2 projects
- City of Los Angeles Bureau of Engineering · 2 projects
Is this your business?
Claim it on Atriam to add your work photos, service area and a booking link, and to run calls, leads, estimates and invoices in one place — free.
Claim this business